Report to the SSC-Sept 10/01
Page 2
Recent Progress
•DEIMOS on tracks and moved onto kinematics mounts •All stages under keyword control including grating transport
•Gratings clamp up at all positions
•Optical alignment done
•FC spots on both FC detectors for stages for all stages
•X and Y FC stages characterized
•