"Report to the SSC"
Report to the SSC
Sept 10, 2001

Recent Progress
DEIMOS on tracks and moved onto kinematics mounts
All stages under keyword control including grating transport
Gratings clamp up at all positions
Optical alignment done
FC spots on both FC detectors for stages for all stages
X and Y FC stages characterized

Recent Progress
TV mounted, image motion 3 arc sec (pk-pk), rotation small
LN2 can complete and in testing
Readiness Review held on Aug 21-23
Tractor testing to start this week
Pre Ship Review planned Sept 24-25

Key Dates
Sept 24-25 Preship Review
Oct 8 Start disassembly
Nov 2 Ship mainframe via sea
Nov 8 Mainframe arrives on big island
Nov 15 Hoist MF into K2 dome
Nov 26-30th Test tractor and kinematics on K2
Dec 6-10th Install slitmask system

Key Dates
Dec 10-17th Install grating system
Dec 18-10th Install TV system
Dec 22-Jan 5th Home for Christmas
Jan 8-10th Test nose area systems
Jan 11th Install camera
Jan 17th Install dewar
Jan 24-30th Alignment
Jan 31-Feb 14th Testing
Feb 28th First Light

Effect of PI’s Accident
What Sandy can do now: 10 hours/day
Sit in recliner chair
Get around house slowly with walker
Talk on phone/conference calls
Send/receive faxes
Write longhand
Read/think
2. Added activities this next week:
Computer and e-mail

Effect of PI’s Accident
Ways in which Sandy will be able to help more:
Talking to key people more frequently
Merging information
Minute-to-minute planning with Dave and other unit leaders

Effect of PI’s Accident
Ways in which Sandy will be able to help less:
Reduced oversight and motivating role in Instrument Shop
Reduced insight into test results
No image analysis
Less Zemax modeling, including loss of room-temperature Zemax model for current optical performance (had been promised at PSR)
Net result:
Better high-level functioning
Reduced low-level functioning

Flexure
Slider 2 (mirror, direct imaging)
X=9 px pk-pk, y=14 px pk-pk
Rotation: 0.5 px pk-pk center to edge
Slider 3 (grating)
X=20 px pk-pk, y=13 px pk-pk
Rotation: 1.3 px pk-pk  center to edge
Slider 4 (grating)
X=16 px pk-pk, y=9 px pk-pk
Rotation: 0.7 px pk-pk center to edge

Flexure
Slider 3 was predicted by FEA to be the worst case
Marked hysteresis is present depending on PA rotation direction; working FC system is needed
Grating transport system increases flexure when grating inserted at PA angle 0 degrees on sliders 3 &4 (we are working on this)
Capture range of FC system (from actual tests)
X=26 px pk-pk, y=21 px pk-pk

Flexure - Sources
Collimator 4 4
Detector 4 4
Camera* 13 13
Grating box 5 5
Grating sliders 6 6
*Also affect image quality: variable comatic tails

Camera Flexure
Curing flexure in camera is expected to reduce the observed x flexure greatly but increase y flexure a small amount

DEIMOS Camera
The Problem
We believe that it is either cell 4, which has three degrees of adjustment designed into it, or element 3, which is coupled to its cell with shims. All other elements are cemented into place with the exception of element 5, which is held in place by elements 4 and 6.

DEIMOS Camera
Motion in camera confirmed by two independent methods
Double-pass test using a point source at the focal plane, a mirror at the front of the camera, and the Cohu detector, does not need spectrograph or science detector
Analysis by of ghost images taken with the 900 line grating; separately measured detector motion must be subtracted off
Two test agree well

DEIMOS Camera
Original tests in the optics lab did not look for image motion. We tested for image quality using a microscope and the Cohu detector on and off axis. The off axis tests were done at 4 different position angles of the camera by rotating the camera

DEIMOS Camera
Planned Tests before Removal from Instrument
Mahr gage tests directly measuring the motion of cell 4 using pre-existing holes in the camera body.
Pinhole test which will look at the shadows of 2 rings on the back face of element 8 in cell 4. From the magnitude of the motion, we should be able to determine where the moving element in the camera is.

DEIMOS Camera
 Planned tests before removal from Instrument
Repeat the double-pass test with the Cohu detector and fiber once dewar is removed from DEIMOS; this will be the key diagnostic test used in the optical lab during the repair process. Measures both the image motion and image quality.

DEIMOS Camera
Repair Plan
Remove the camera from DEIMOS and mount it in a horizontal rotator in the Optics lab, and repeat the double-pass test using the Cohu camera. The camera was in this rotator for the initial optical tests following assembly

DEIMOS Camera
Repair Plan
Remove camera from rotator and disassemble cell 4 from camera.
Test cell 4 for flexure using Mahr gauges
Note this cell has both radial and axial flexures
If translation is caused by radial flexures, remove and replace springs
If translation is caused by axial flexure, re-make flexures

DEIMOS Camera
Repair Plan
If flexure not found in Cell 4, further disassemble camera to Cell 2 which holds element 3 of the camera
Problem may be with shims between element and cell. They may be too small or have fallen out. If so, they will be fixed.
Reassemble camera and test in rotator using the double-pass test and the Cohu detector

Camera Repair Schedule
Oct 8th Double-pass test with Cohu detector following removal of dewar
Oct 9th Removal of camera from DEIMOS
Oct 10-16th Camera tests in Optics Lab
Oct 17-Nov 5thDisassemble, test and repair

Camera Repair Schedule
Nov 5-9th Assemble camera
Nov 12-16th Test camera on test stand
Nov 18-20th Disassemble and pack camera
Nov 26th Ship to Hawaii
Nov 27-Dec 3rd Assemble camera in HI
Jan 11th Install camera in DEIMOS

Camera Risks and Fallbacks
Testing camera outside DEIMOS in optical lab is not deemed a major risk; Cohu test is good
Risk 1: task is straightforward but takes longer than planned; Vernon Wallace needed to repair camera (ends Nov 26) and to install slitmask system (Dec 3)
Mitigation- Jeff Lewis is experienced with installing slitmask system

Camera Risks and Fallbacks
Risk 2: Solution requires major rebuild of Body 4 axial flexure
Mitigation: We have thought of a better way to fabricate these flexures
Conclude: Less risk to overall schedule by shipping DEIMOS while repairing camera here

DEIMOS Concerns
Larger image motion when slides clamped at PA 0; need to fix this
Finish trolley and test
Adequate test time for all stages; time to analyze and digest test data
DS 9
Observers GUI
Camera flexure (after PSR)
Commission Slider 5 (after PSR)
Red Science array (after PSR)