"Report to the SSC"
|
|
|
Report to the SSC |
|
Sept 10, 2001 |
Recent Progress
|
|
|
DEIMOS on tracks and moved onto
kinematics mounts |
|
All stages under keyword control
including grating transport |
|
Gratings clamp up at all positions |
|
Optical alignment done |
|
FC spots on both FC detectors for
stages for all stages |
|
X and Y FC stages characterized |
|
|
Recent Progress
|
|
|
TV mounted, image motion 3 arc sec
(pk-pk), rotation small |
|
LN2 can complete and in testing |
|
Readiness Review held on Aug 21-23 |
|
|
|
Tractor testing to start this week |
|
Pre Ship Review planned Sept 24-25 |
|
|
Key Dates
|
|
|
Sept 24-25 Preship Review |
|
Oct 8 Start disassembly |
|
Nov 2 Ship mainframe via sea |
|
Nov 8 Mainframe arrives on big
island |
|
Nov 15 Hoist MF into K2 dome |
|
Nov 26-30th Test tractor
and kinematics on K2 |
|
Dec 6-10th Install
slitmask system |
Key Dates
|
|
|
Dec 10-17th Install grating system |
|
Dec 18-10th Install TV system |
|
Dec 22-Jan 5th Home for Christmas |
|
Jan 8-10th Test nose area systems |
|
Jan 11th Install camera |
|
Jan 17th Install dewar |
|
Jan 24-30th Alignment |
|
Jan 31-Feb 14th Testing |
|
Feb 28th First Light |
Effect of PI’s Accident
|
|
|
|
What Sandy can do now: 10 hours/day |
|
Sit in recliner chair |
|
Get around house slowly with walker |
|
Talk on phone/conference calls |
|
Send/receive faxes |
|
Write longhand |
|
Read/think |
|
2. Added activities this next week: |
|
Computer and e-mail |
|
|
Effect of PI’s Accident
|
|
|
|
Ways in which Sandy will be able to
help more: |
|
Talking to key people more frequently |
|
Merging information |
|
Minute-to-minute planning with Dave and
other unit leaders |
|
|
Effect of PI’s Accident
|
|
|
|
Ways in which Sandy will be able to
help less: |
|
Reduced oversight and motivating role
in Instrument Shop |
|
Reduced insight into test results |
|
No image analysis |
|
Less Zemax modeling, including loss of
room-temperature Zemax model for current optical performance (had been
promised at PSR) |
|
Net result: |
|
Better high-level functioning |
|
Reduced low-level functioning |
Flexure
|
|
|
|
Slider 2 (mirror, direct imaging) |
|
X=9 px pk-pk, y=14 px pk-pk |
|
Rotation: 0.5 px pk-pk center to edge |
|
Slider 3 (grating) |
|
X=20 px pk-pk, y=13 px pk-pk |
|
Rotation: 1.3 px pk-pk center to edge |
|
Slider 4 (grating) |
|
X=16 px pk-pk, y=9 px pk-pk |
|
Rotation: 0.7 px pk-pk center to edge |
|
|
|
|
Flexure
|
|
|
|
Slider 3 was predicted by FEA to be the
worst case |
|
Marked hysteresis is present depending
on PA rotation direction; working FC system is needed |
|
Grating transport system increases
flexure when grating inserted at PA angle 0 degrees on sliders 3 &4 (we
are working on this) |
|
Capture range of FC system (from actual
tests) |
|
X=26 px pk-pk, y=21 px pk-pk |
Flexure - Sources
|
|
|
Collimator 4 4 |
|
Detector 4 4 |
|
Camera* 13 13 |
|
Grating box 5 5 |
|
Grating sliders 6 6 |
|
*Also affect image quality: variable
comatic tails |
|
|
Camera Flexure
|
|
|
Curing flexure in camera is expected to
reduce the observed x flexure greatly but increase y flexure a small amount |
DEIMOS Camera
The Problem
|
|
|
|
|
We believe that it is either cell 4,
which has three degrees of adjustment designed into it, or element 3, which
is coupled to its cell with shims. All other elements are cemented into place
with the exception of element 5, which is held in place by elements 4 and 6. |
DEIMOS Camera
|
|
|
|
Motion in camera confirmed by two
independent methods |
|
Double-pass test using a point source
at the focal plane, a mirror at the front of the camera, and the Cohu
detector, does not need spectrograph or science detector |
|
Analysis by of ghost images taken with
the 900 line grating; separately measured detector motion must be subtracted
off |
|
Two test agree well |
|
|
DEIMOS Camera
|
|
|
Original tests in the optics lab did
not look for image motion. We tested for image quality using a microscope and
the Cohu detector on and off axis. The off axis tests were done at 4
different position angles of the camera by rotating the camera |
DEIMOS Camera
Planned
Tests before Removal from Instrument
|
|
|
Mahr gage tests directly measuring the
motion of cell 4 using pre-existing holes in the camera body. |
|
Pinhole test which will look at the
shadows of 2 rings on the back face of element 8 in cell 4. From the
magnitude of the motion, we should be able to determine where the moving
element in the camera is. |
|
|
DEIMOS Camera
Planned
tests before removal from Instrument
|
|
|
Repeat the double-pass test with the
Cohu detector and fiber once dewar is removed from DEIMOS; this will be the
key diagnostic test used in the optical lab during the repair process.
Measures both the image motion and image quality. |
DEIMOS Camera
Repair Plan
|
|
|
Remove the camera from DEIMOS and mount
it in a horizontal rotator in the Optics lab, and repeat the double-pass test
using the Cohu camera. The camera was in this rotator for the initial optical
tests following assembly |
DEIMOS Camera
Repair Plan
|
|
|
|
Remove camera from rotator and
disassemble cell 4 from camera. |
|
Test cell 4 for flexure using Mahr
gauges |
|
Note this cell has both radial and
axial flexures |
|
If translation is caused by radial
flexures, remove and replace springs |
|
If translation is caused by axial
flexure, re-make flexures |
DEIMOS Camera
Repair Plan
|
|
|
|
If flexure not found in Cell 4, further
disassemble camera to Cell 2 which holds element 3 of the camera |
|
Problem may be with shims between
element and cell. They may be too small or have fallen out. If so, they will
be fixed. |
|
Reassemble camera and test in rotator
using the double-pass test and the Cohu detector |
|
|
Camera Repair Schedule
|
|
|
Oct 8th Double-pass
test with Cohu detector following removal of
dewar |
|
Oct 9th Removal of
camera from DEIMOS |
|
Oct 10-16th Camera tests
in Optics Lab |
|
Oct 17-Nov 5thDisassemble,
test and repair |
Camera Repair Schedule
|
|
|
Nov 5-9th Assemble camera |
|
Nov 12-16th Test camera
on test stand |
|
Nov 18-20th Disassemble
and pack camera |
|
Nov 26th Ship to
Hawaii |
|
Nov 27-Dec 3rd Assemble
camera in HI |
|
Jan 11th Install
camera in DEIMOS |
Camera Risks and
Fallbacks
|
|
|
|
|
Testing camera outside DEIMOS in
optical lab is not deemed a major risk; Cohu test is good |
|
Risk 1: task is straightforward but
takes longer than planned; Vernon Wallace needed to repair camera (ends Nov
26) and to install slitmask system (Dec 3) |
|
Mitigation- Jeff Lewis is experienced
with installing slitmask system |
Camera Risks and
Fallbacks
|
|
|
|
|
Risk 2: Solution requires major rebuild
of Body 4 axial flexure |
|
Mitigation: We have thought of a better
way to fabricate these flexures |
|
Conclude: Less risk to overall schedule
by shipping DEIMOS while repairing camera here |
DEIMOS Concerns
|
|
|
Larger image motion when slides clamped
at PA 0; need to fix this |
|
Finish trolley and test |
|
Adequate test time for all stages; time
to analyze and digest test data |
|
DS 9 |
|
Observers GUI |
|
Camera flexure (after PSR) |
|
Commission Slider 5 (after PSR) |
|
Red Science array (after PSR) |
|
|
|
|
|
|