Key Dates
•
Sept 24-25
Preship Review
•
Oct 8
Start disassembly
•
Nov 2
Ship mainframe via sea
•
Nov 8
Mainframe arrives on big island
•
Nov 15
Hoist MF into K2 dome
•
Nov 26-30
th
Test tractor and kinematics on K2
•
Dec 6-10
th
Install slitmask system