Report to the SSC-Jan 10/02
Page 2
Key Dates
•Nov 13-14/01 Preship Review
•Jan 4/02 Final review before disassembly
•Jan 7 Start disassembly
•Feb 8 Ship mainframe via sea
•Feb 17 Mainframe arrives on big island
•Feb 21 Hoist MF into K2 dome
•Feb 26-Mar 1 Test tractor and kinematics on K2
•Mar 14 Install slitmask system