Report to the SSC-Jan 10/02
Page 3
Key Dates
•Mar 18-22 Install grating system
•Mar 26 Install TV system
•Apr 1-2 Test nose area systems
•Apr 5 Install camera
•Apr 12 Install dewar
•May 5-8 Alignment
•Apr 25-May15 Testing
•Jun 2 First Light