Report to the SSC-Jan 10/02
Page
3
Key Dates
•
Mar 18-22
Install grating system
•
Mar 26
Install TV system
•
Apr 1-2
Test nose area systems
•
Apr 5
Install camera
•
Apr 12
Install dewar
•
May 5-8
Alignment
•
Apr 25-May15
Testing
•
Jun 2
First Light