"Report to the SSC"
Report to the SSC
Jan 10, 2002

Key Dates
Nov 13-14/01 Preship Review
Jan 4/02 Final review before disassembly
Jan 7 Start disassembly
Feb 8 Ship mainframe via sea
Feb 17 Mainframe arrives on big island
Feb 21 Hoist MF into K2 dome
Feb 26-Mar 1 Test tractor and kinematics on K2
Mar 14 Install slitmask system

Key Dates
Mar 18-22 Install grating system
Mar 26 Install TV system
Apr 1-2 Test nose area systems
Apr 5 Install camera
Apr 12 Install dewar
May 5-8 Alignment
Apr 25-May15 Testing
Jun 2 First Light

Summary Budget
Cumulative Last Quarter
(Nov 31/01)
Labor: $6,162,220 $411,469
Materials & Supplies $2,895,555 $102,939
Totals $9,057,775 $514,400
Approved Budget $8,958,864   (July 01 est for first light
Feb 26/02)
Remaining Budget     ($98,911)

Commissioning Costs

Other Major Expenses
Coating of Mirrors $35,000