| Report to the SSC | |
| Jan 10, 2002 |
| Nov 13-14/01 Preship Review | |
| Jan 4/02 Final review before disassembly | |
| Jan 7 Start disassembly | |
| Feb 8 Ship mainframe via sea | |
| Feb 17 Mainframe arrives on big island | |
| Feb 21 Hoist MF into K2 dome | |
| Feb 26-Mar 1 Test tractor and kinematics on K2 | |
| Mar 14 Install slitmask system |
| Mar 18-22 Install grating system | |
| Mar 26 Install TV system | |
| Apr 1-2 Test nose area systems | |
| Apr 5 Install camera | |
| Apr 12 Install dewar | |
| May 5-8 Alignment | |
| Apr 25-May15 Testing | |
| Jun 2 First Light |
| Cumulative Last Quarter | |
| (Nov 31/01) | |
| Labor: $6,162,220 $411,469 | |
| Materials & Supplies $2,895,555 $102,939 | |
| Totals $9,057,775 $514,400 | |
| Approved Budget $8,958,864 (July 01 est for first light | |
| Feb 26/02) | |
| Remaining Budget ($98,911) | |
| Coating of Mirrors $35,000 |