Report to the SSC | |
Jan 10, 2002 |
Nov 13-14/01 Preship Review | |
Jan 4/02 Final review before disassembly | |
Jan 7 Start disassembly | |
Feb 8 Ship mainframe via sea | |
Feb 17 Mainframe arrives on big island | |
Feb 21 Hoist MF into K2 dome | |
Feb 26-Mar 1 Test tractor and kinematics on K2 | |
Mar 14 Install slitmask system |
Mar 18-22 Install grating system | |
Mar 26 Install TV system | |
Apr 1-2 Test nose area systems | |
Apr 5 Install camera | |
Apr 12 Install dewar | |
May 5-8 Alignment | |
Apr 25-May15 Testing | |
Jun 2 First Light |
Cumulative Last Quarter | |
(Nov 31/01) | |
Labor: $6,162,220 $411,469 | |
Materials & Supplies $2,895,555 $102,939 | |
Totals $9,057,775 $514,400 | |
Approved Budget $8,958,864 (July 01 est for first light | |
Feb 26/02) | |
Remaining Budget ($98,911) | |
Coating of Mirrors $35,000 |