•Lift to rails
Nov 15 –Puna Crane, telescope down for morning
•Test carriage system Nov
28, 29
•Complete Camera Ass Dec
6
•Install slitmask sys Dec 6
•Install grating sys Dec 10
•Install inst computer Dec
10
•Install TV Dec 18
•Install camera Jan 11
–need Jib Crane
•Install collimator Jan 15 –need Jib Crane
•Install tent mirror Jan 16
•Install dewar Jan 17
–need Jib Crane
•