Commissioning Plans
Key Dates
Mon Jan 7 – (11 people arrive back in Hawaii to continue)
Fri Jan 18 – (5 people depart with the end of major assembly)
 Mon Jan 21 – (2 Software people arrive)
Thurs Jan 31 – start of full up instrument tests
Thurs Feb 28 – first star light