Lift
to rails Nov 15 –Puna Crane,
telescope down for
|
|
morning
|
|
|
• |
Test
carriage system Nov 28, 29
|
|
|
• |
Complete
Camera Ass Dec 6
|
|
|
• |
Install
slitmask sys Dec 6
|
|
|
• |
Install
grating sys Dec 10
|
|
|
• |
Install
inst computer Dec 10
|
|
|
• |
Install
TV Dec 18
|
|
|
• |
Install
camera Jan 11 –need Jib Crane
|
|
|
• |
Install
collimator Jan 15 –need Jib Crane
|
|
|
• |
Install
tent mirror Jan 16
|
|
|
• |
Install
dewar Jan 17 –need Jib Crane
|
|