Sequence of major events
Lift to rails     Nov 15 –Puna Crane, telescope down for
           morning
Test carriage system   Nov 28, 29
Complete Camera Ass   Dec 6
Install slitmask sys   Dec 6
Install grating sys   Dec 10
Install inst computer   Dec 10
Install TV     Dec 18
Install camera     Jan 11 –need Jib Crane
Install collimator   Jan 15 –need Jib Crane
Install tent mirror    Jan 16
Install dewar     Jan 17 –need Jib Crane